Skip To Main Content

JFK HS Bond Budget

JFK High School Proposed Bond-Funded Projects and Costs

JFK Bond Budget PDF PDF del presupuesto del bono JFK

 

* Construction Costs Include: Oregon Solar Rqd, Permits & Land Use, Survey: Boundary & Topography, Geotechnical Investigation, Bond Issuance Cost & Program Mgmt, Furnishings, 15% Contingency, Design Fees, School District Hired Construction Specialist - Commissioning - Envelope Consultant - Cost Estimating

* ODE Escalation - ODE inflation rate is 14% over 30 months (5.6%/yr). Assumes 1 year to bond passage. Assumes 1.5 - 3 years of design & construction cycle

Category Project Original Estimate from 2021 Facility Assessment Report (BLRB Architects)

38% Construction costs

ODE Escalation to May 2024 - 14% Budget from
2021 Long Range Facility Plan

(with construction costs and ODE inflation rate)
Category Subtotals Rounded for Bond Planning
Architectural Replace remaining old windows       $141,000    
  Interior finish upgrades $25,000 $34,500 $4,830 $39,330    
  Toilet room upgrades $150,000 $207,000 $28,980 $235,980    
  Replace classroom door hardware with secure hardware $100,000 $138,000 $19,320 $157,320 $573,630 $580,000
 
Plumbing Plumbing fixture replacements $23,599 $32,567 $4,559 $37,126    
  Domestic water system improvements $20,733 $28,612 $4,006 $32,617    
  Sanitary waste improvements $10,586 $14,609 $2,045 $16,654 $86,397 $90,000
 
HVAC Air Handler $38,999 $53,819 $7,535 $61,353    
  Heat exchanger $95,339 $131,568 $18,419 $149,987    
  Ductwork $36,207 $49,966 $6,995 $56,961    
  Boiler hot water distribution system $577,835 $797,412 $111,638 $909,050    
  In-room ventilator units $100,000 $138,000 $19,320 $157,320    
  HVAC controls system $181,374 $250,296 $35,041 $285,338    
  Testing & balancing $29,532 $40,754 $5,706 $46,460 $1,666,469 $1,700,000
 
Electrical Replace outdated electrical panels $317,067 $437,552 $61,257 $498,810    
  Replace/retrofit fluorescent fixtures with LED fixtures $160,000 $220,800 $30,912 $251,712    
  Voice / Data System upgrades $12,305 $16,981 $2,377 $19,358    
  Provide access controls at exterior doors $50,000 $69,000 $9,660 $78,660 $848,540 $850,000
 
Site Sewer Repairs at Stadium Concessions $75,000 $103,500 $14,490 $117,990 $117,990 $120,000
              $3,340,000
 
MT. ANGEL MIDDLE SCHOOL TOTAL $3,260,000
ST. MARY’S PUBLIC SCHOOL TOTAL $4,360,000
BUS BARN TOTAL $40,000
PROPOSED BOND TOTAL $11,000,000